Crushed Stone Calculator

Choose the stone grade, enter your area and depth, and get the tons and cubic yards of crushed stone you need. The calculator adds 15 percent by default, because crushed stone packs down when it’s compacted.

ft
ft
ft
sq ft
in
tons/yd³
Extra for compaction and cost
%
$
–cubic yards

–tons
–bags (0.5 cu ft)
–sq ft area
–estimated cost

Weights are typical for dry, loose material. Your supplier's figure may differ slightly.

Crushed stone grades explained

Crushed stone is sold by size number. The numbers are standard size grades used by quarries in the US, although local names vary, so check with your supplier if a name doesn’t match.

GradeSizeWeight per cubic yardCommon uses
#3 stone1½–2 inabout 1.30 tonsDriveway base layers, erosion control
#57 stone¾–1 inabout 1.35 tonsDrainage, French drains, driveway middle layers
#8 stone⅜–½ inabout 1.35 tonsDrainage around pipes, top dressing
#411#57 mixed with stone dustabout 1.45 tonsDriveway top layers, walkways
Crusher run / dense grade¾ in down to dustabout 1.55 tonsCompacted base under pavers, slabs and sheds
Stone dust / screenings¼ in and finerabout 1.40 tonsSetting bed for pavers and flagstone

Clean stone or dense-graded?

Clean stone (#3, #57, #8) has no fine dust. Water drains straight through it, which is why it’s used for drainage. It doesn’t lock together into a hard surface on its own.

Dense-graded stone (crusher run, #411) includes fine particles that fill the gaps. When it’s compacted it becomes firm and solid, which makes it the usual choice for bases under pavers, sheds and driveways. It drains more slowly than clean stone.

Typical depths

  • Shed base or walkway base: 4 to 6 inches of compacted dense-graded stone.
  • Paver patio base: commonly 4 to 6 inches, plus about an inch of sand or stone dust on top.
  • Driveway: 8 to 12 inches in layers. The gravel driveway calculator handles each layer separately.
  • Drainage trench: fill the trench with clean #57 stone around the pipe.

Worked example

A 10 ft × 12 ft shed base, 4 inches deep, in #57 stone:

  • 10 × 12 = 120 square feet
  • 120 × 4 ÷ 12 = 40 cubic feet, or 1.48 cubic yards
  • With 15 percent extra for compaction: 1.70 cubic yards
  • 1.70 × 1.35 = about 2.30 tons

Why add extra for compaction?

Stone arrives loose. Once it’s spread and run over with a plate compactor, the pieces settle into the gaps and the layer gets thinner. Ordering 10 to 15 percent extra means you still finish at the depth you planned. For decorative stone that isn’t compacted, 5 to 10 percent is usually enough.

Frequently asked questions

How many tons are in a cubic yard of crushed stone?

About 1.35 tons for clean stone like #57, and around 1.45 to 1.55 tons for dense-graded mixes like #411 and crusher run, which contain fine particles.

How much does a ton of crushed stone cover?

A ton of #57 stone is about 20 cubic feet. That covers about 60 square feet at 4 inches deep, or 80 square feet at 3 inches.

What size crushed stone is best for drainage?

Clean stone with no fines, such as #57 or #3. Water passes through the gaps between the stones.

What should I use under pavers or a shed?

A dense-graded stone such as crusher run, compacted in layers. It forms a firm base that won’t shift.

Is crushed stone the same as gravel?

Not quite. Crushed stone is made by crushing rock, so the pieces are sharp and angular and lock together. Gravel often means naturally rounded stone, like pea gravel or river rock, which stays loose.